title: "Plan a shutdown on a critical path"
description: "When a plant shutdown is approved, I want every job, craft, contractor and permit on one critical-path plan with live progress, so I can bring the plant…"
author: Mapped
license: https://creativecommons.org/licenses/by/4.0/
canonical: https://rivet.mapped.com/personas/job/manufacturing/maintenance-planner-scheduler/plan-a-shutdown-on-a-critical-path
---

# Plan a shutdown on a critical path

Job to be done · Maintenance Planner / Scheduler

In [Maintenance](https://rivet.mapped.com/personas/category/maintenance) · for the [Maintenance Planner / Scheduler](https://rivet.mapped.com/personas/role/manufacturing/maintenance-planner-scheduler) in [Manufacturing plants and industrial sites](https://rivet.mapped.com/personas/facility/manufacturing)

> When a plant shutdown is approved, I want every job, craft, contractor and permit on one critical-path plan with live progress, so I can bring the plant back on time and show what slipped and why.

## Apps that fit

Schedule · Board · Report

## Measured by

- shutdown duration vs plan
- jobs completed vs scoped
- contractor hours

## What an app needs to see

- shutdown work list with durations and dependencies
- permit/LOTO status
- contractor check-in
- progress updates

## Pain points

- Shutdown planning requires multi-craft sequencing, contractor coordination and critical-path scheduling in Project or P6 (JD template)
- Involving younger staff in shutdown planning is a recommended knowledge-transfer tactic (Plant Engineering)

## Who else wants this

### Airports

- Airport Wildlife Biologist: [See wildlife activity and strikes by zone and season](https://rivet.mapped.com/personas/job/airport/airport-wildlife-biologist/see-wildlife-activity-and-strikes-by-zone-and-season)
- Airside / Airfield Operations Manager: [Coordinate gates and diversions quickly](https://rivet.mapped.com/personas/job/airport/airside-operations-manager/coordinate-gates-and-diversions-quickly)
- Environmental / Sustainability Manager: [Build the ghg inventory from live data](https://rivet.mapped.com/personas/job/airport/environmental-sustainability-manager/build-the-ghg-inventory-from-live-data)
- Environmental / Sustainability Manager: [Stay inside the stormwater and glycol permit](https://rivet.mapped.com/personas/job/airport/environmental-sustainability-manager/stay-inside-the-stormwater-and-glycol-permit)

### Data center

- Critical Facilities Supervisor / Shift Lead: [Keep the crew safe on energized work](https://rivet.mapped.com/personas/job/data-center/critical-facilities-supervisor/keep-the-crew-safe-on-energized-work)
- Change Manager / MOP Coordinator: [Oversee the change window live](https://rivet.mapped.com/personas/job/data-center/change-manager-mop-coordinator/oversee-the-change-window-live)

### Government, civic and public-safety buildings

- Stationary Engineer / Building Engineer: [Keep heat and cooling on for a building that cannot close](https://rivet.mapped.com/personas/job/government-civic/stationary-engineer-building-engineer/keep-heat-and-cooling-on-for-a-building-that-cannot-close)

### Manufacturing plants and industrial sites

- Sanitation Manager (food & beverage): [Finish sanitation inside the window](https://rivet.mapped.com/personas/job/manufacturing/sanitation-manager-food/finish-sanitation-inside-the-window)

## Sources

- [Maintenance Planner/Scheduler job description template](https://www.mangoapps.com/templates/recruiting_job/maintenance-planner-scheduler-job-description)
- [Plant Engineering: Plants without a succession plan are vulnerable to disruption](https://www.plantengineering.com/plants-without-a-succession-plan-are-vulnerable-to-disruption/)

## More jobs for the Maintenance Planner / Scheduler

[See the backlog by stage and age](https://rivet.mapped.com/personas/job/manufacturing/maintenance-planner-scheduler/see-the-backlog-by-stage-and-age) · [Schedule against real production windows](https://rivet.mapped.com/personas/job/manufacturing/maintenance-planner-scheduler/schedule-against-real-production-windows) · [Kit parts before the job](https://rivet.mapped.com/personas/job/manufacturing/maintenance-planner-scheduler/kit-parts-before-the-job) · [Measure planning not people](https://rivet.mapped.com/personas/job/manufacturing/maintenance-planner-scheduler/measure-planning-not-people)

## Every kind of facility

[Airports](https://rivet.mapped.com/personas/facility/airport) · [Cross-cutting and portfolio roles](https://rivet.mapped.com/personas/facility/cross-cutting) · [Data center](https://rivet.mapped.com/personas/facility/data-center) · [Education campuses](https://rivet.mapped.com/personas/facility/education) · [Government, civic and public-safety buildings](https://rivet.mapped.com/personas/facility/government-civic) · [Hospitals and healthcare facilities](https://rivet.mapped.com/personas/facility/healthcare) · [Laboratories and life-science facilities](https://rivet.mapped.com/personas/facility/laboratory) · [Manufacturing plants and industrial sites](https://rivet.mapped.com/personas/facility/manufacturing) · [Multifamily residential and rental housing](https://rivet.mapped.com/personas/facility/multifamily-residential) · [Office buildings and corporate workplaces](https://rivet.mapped.com/personas/facility/office) · [Retail, hospitality and venues](https://rivet.mapped.com/personas/facility/retail-hospitality) · [Transit, terminals and parking](https://rivet.mapped.com/personas/facility/transit-parking) · [Utilities and critical process infrastructure](https://rivet.mapped.com/personas/facility/utilities-infrastructure) · [Warehouses and distribution centers](https://rivet.mapped.com/personas/facility/warehouse)

## Every job category

[Uptime](https://rivet.mapped.com/personas/category/uptime) · [Maintenance](https://rivet.mapped.com/personas/category/maintenance) · [Energy](https://rivet.mapped.com/personas/category/energy) · [Sustainability](https://rivet.mapped.com/personas/category/sustainability) · [Safety](https://rivet.mapped.com/personas/category/safety) · [Compliance](https://rivet.mapped.com/personas/category/compliance) · [Security](https://rivet.mapped.com/personas/category/security) · [Space](https://rivet.mapped.com/personas/category/space) · [Occupancy](https://rivet.mapped.com/personas/category/occupancy) · [Experience](https://rivet.mapped.com/personas/category/experience) · [Cost](https://rivet.mapped.com/personas/category/cost) · [Capital planning](https://rivet.mapped.com/personas/category/capital_planning) · [Workforce](https://rivet.mapped.com/personas/category/workforce) · [Vendor](https://rivet.mapped.com/personas/category/vendor) · [Throughput](https://rivet.mapped.com/personas/category/throughput) · [Quality](https://rivet.mapped.com/personas/category/quality) · [Customer](https://rivet.mapped.com/personas/category/customer) · [IT and OT](https://rivet.mapped.com/personas/category/it_ot) · [Cleaning](https://rivet.mapped.com/personas/category/cleaning) · [Resilience](https://rivet.mapped.com/personas/category/resilience)

---

From [PersonaDB](https://rivet.mapped.com/personas), Mapped’s directory of who works in a facility and what they’re trying to get done, free to reuse under CC BY 4.0 (https://creativecommons.org/licenses/by/4.0/) with credit to Mapped. Page: https://rivet.mapped.com/personas/job/manufacturing/maintenance-planner-scheduler/plan-a-shutdown-on-a-critical-path